| Project | Last updated | Projected Completion | Details |
| Building 13 Balcony repairs | 9-4-26 | TBD | Some balconies permits have been completed and are closed up. Inspector delayed on a few others. |
| Building 9 Balcony repairs | 9-4-26 | TBD | Some balconies permits have been completed and are closed up. Inspector delayed on a few others. |
|
Pace Protection Camera Upgrades |
9-4-26 | TBD | Approved project, materials are being ordered and conversion project will begin when all materials have arrived |
| Stairwell Project | 9-4-26 | TBD | Gathering Bids from several vendors to determine overall cost of repairs |
| New Dumpster Service | 9-4-26 | TBD |
Previous recycle containers pending removal. All new containers have been delivered. Request for update sent to hauler |
| Building 8 Balcony Repairs | 9-4-26 | 9-30-26 | Work Ongoing, Contractor delayed for permitting and Engineer review. |
| Building 12 Balcony Repairs | 9-4-26 | TBD | Pending permits |
| Sprinkler head repairs | 9-4-26 | TBD | Confirming labor cost nubmers with Thompson Fire. |
| Balconies that are pending permits will have a cover put on the inspection hole to prevent pests from entering. |